Construction Management & scheduling
Assignment 4
Q1. A project consists of replacing the track on an existing railroad line, involving 3,000 feet of
track. The old track can be removed at a rate of 70 feet per hour. The old railroad ties can be
removed at a rate of 200 feet (measured along the track) per hour. The new ties can be installed
at a rate of 25 feet per hour and the replacement track can be installed at a rate of 40 feet per
hour. Show this operation on a linear schedule. Assume that the minimum float for an activity at
any location is one day. 40 points
Q2. Describe a project that might not be well suited for linear scheduling. Please provide good
explanation of the project and the reasons why linear scheduling is not suitable for that project.
20 Points
Q3. Create a linear schedule for highway project 15 miles long considering following
information
(Please round to the nearest integer for duration in days). 40 points
Activity Productivity rate (miles/day) Time buffer (days)
Survey and
layout
2.5
Clear and Grub 0.75 1
Earthwork 0.36 for the first 5 mile
2 idle days
After the idle days, 1 miles for rest of the miles
1
Sub-base 1.0 17
Base 1.0 1
Paving 3 11
Signage 7.5 3